Slavyanskaya TPP risks not being repaired before cold weather
Kyiv, July 16 (Navigator, Vladimir Mikhailov) – The most costly task in establishing the energy system of Slavyansk is the restoration of the local thermal power plant, said Deputy Director of the Electric Power Department of the Ministry of Energy and Coal of Ukraine Boris Sorkin, speaking at the round table “Restoring the infrastructure of the liberated territories of Donbass”.
Subscribe to Navigator Kyiv news on Facebook , Odnoklassniki , or VKontakte
“In Slavyansk, power supply has been restored to more than 60% of the city; work is now underway to restore two central substations, 110 kW, which, if turned on, will be able to restore another 30% of the city; it is planned to be completed on Friday. By Friday there are hopes that 90% of the city will be powered. The completion of restoration work in Slavyansk is planned in a week,” said Boris Sorokin.
According to him, the restoration of the Slavyanskaya Thermal Power Plant is the most costly. According to the Ministry of Energy and Coal Industry, the damage to the Slavyanskaya Thermal Power Plant is now estimated at almost half a billion hryvnia.
“And the assessment is not yet complete. The buildings have not yet been inspected; serious work needs to be done to control the building structures, equipment of the boiler and turbine shops, so the assessments will still change.
This causes concern for the ministry specifically from the point of view of the autumn-winter period,” he said.
Slavyansk Thermal Power Plant is at risk of not being repaired before the cold weather sets in.