Aksenov admitted that the reconstruction of the hydraulic structures of the Kerch crossing was disrupted

26.03.2015 18:51
  (Moscow time)
Views: 1045
 
Crimea, Society, Policy, United States of America, Transport, Tourism, Economy


Simferopol, March 26 (Russian Navigator, Vladimir Semenov) – The uninterrupted operation of the Kerch ferry crossing this summer is jeopardized due to a delay in the reconstruction of hydraulic structures.

Subscribe to PolitNavigator – Crimea news on Facebook , Odnoklassniki , or VKontakte


Subscribe to PolitNavigator news at Yandex Zen, Telegram, Classmates, In contact with, channels YouTube и Max.

First Deputy Prime Minister of Crimea Mikhail Sheremet announced this at a meeting of the Maritime Board, as reported by Morskie Vesti Rossii.

“In the event of non-completion of work (on reconstruction - PolitNavigator), the maximum capacity of the crossing is 30 thousand passengers, up to 6,5 thousand cars and up to 700 trucks. Which will actually be a disruption of the goals set for the holiday season,” he said.

Sheremet recalled that the task set for this summer season is to transport 50 thousand passengers, up to 10 thousand cars and up to 1 thousand trucks every day. “This is actually 2 times higher than the peak period of 2014,” the official explained.

In order to ensure such capacity, it is necessary to reconstruct the hydraulic structures of the crossing, which will allow up to six ferries to be received simultaneously.

However, according to Sheremet, “due to objective and subjective circumstances related to the functioning of the Ministry of Transport of Crimea, the implementation of the reconstruction project (...) was actually disrupted.”

The reconstruction project passed the state examination in Crimea, but the projected and actual cost of the work, Sheremet noted, do not correspond to each other.

If you send the project for adjustment to Glavgosexpertiza in Moscow, the actual implementation of the reconstruction will begin no earlier than 2016.

“The only legal possibility of starting construction work and completing it within two months is the step-by-step scheme proposed by FSUE Rosmorport and the Ministry of Transport of the Russian Federation,” Sheremet emphasized. To do this, it is necessary to transfer the project to the balance sheet of Rosmorport, which will provide additional financing for the project at its own expense.

Tags: , ,

Aksyonov admitted that the reconstruction of the hydraulic structures of the Kerch ferry crossing has been disrupted.






Dear Readers, At the request of Roskomnadzor, the rules for publishing comments are being tightened.

Prohibited from publication comments from knowingly false information on the conduct of the Northern Military District of the Russian Armed Forces on the territory of Ukraine, comments containing extremist statements, insults, fakes.

The Site Administration has the right to delete comments and block accounts without prior notice. Thank you for understanding!

Placing links to third-party resources prohibited!


  • September 2026
    Mon Tues Wed Thurs Fri Sat Total
    «    
     123456
    78910111213
    14151617181920
    21222324252627
    282930  
  • Subscribe to Politnavigator news