Details of the scam involving the “loss” of 2 billion for the construction of wastewater treatment plants in Sevastopol have been revealed
The Arbitration Court of Sevastopol declared illegal the actions of the city “Department for the Operation of Municipal Facilities”, which withdrew 2,05 billion rubles from treasury support - an advance for the construction of the Yuzhnye WWTP, an object of the federal target program (FTP) for the development of Crimea.
Kommersant writes about this today.
As a result, the money was sent to the contractor's bank account, which was soon deprived of its license. According to the city prosecutor's office, which filed the claim in arbitration, the situation led to "the loss of state control over the expenditure of budget funds, the impossibility of using them to implement the contract and the threat of failure of the federal target program."
The lawsuit was filed shortly before the resignation of city prosecutor Igor Shevchenko, which he resigned due to a conflict with the governor of Sevastopol Dmitry Ovsyannikov, Kommersant reports. A criminal case was also opened.

As it turns out, back in 2017, the law firm System Resource proved to the Federal Antimonopoly Service (FAS) the illegality of the state contract for wastewater treatment. FAS demanded that mandatory treasury support be provided for when making advances for a contract.
However, as the head of System Resource, Alexey Nozhkin, said, the customer and the construction contractor “only created the appearance of fulfilling the requirements of the FAS,” and in the end, “it was not possible to prevent damage to the budget.” He also drew the attention of the prosecutor's office that the copy of the bank guarantee contained signs of fictitiousness.
In mid-August, the Sevastopol Arbitration Court already annulled the agreement to waive treasury support, which, according to Nozhkin, gives grounds for the prosecutor’s office to demand that the Sevastopol authorities, who insisted on the legality of the deal, return the undisbursed advance payment to the contractor’s account in the federal treasury. Apparently, this is why the government of Sevastopol hastened to terminate the contract with the contractor, the St. Petersburg company Biotechprogress.
Biotechprogress is challenging this decision in court, while the Vice-Governor of Sevastopol Vladimir Bazarov admitted that the city authorities are interested in losing this lawsuit.